Brine Line Relocation in Schleisman Avenue

Value: $1,250,000.00 Contractor: Murrieta Development Inc. Designer: TMAD Taylor & Gaines Completed: December 2011

A portion of Schleisman Avenue between Hellman Avenue and the Cucamonga Channel, in the City of Eastvale, is planned for relocation due to development in the area. As part of the relocation of the road the Brine Line must be relocated to within the new road alignment. The Project includes abandoning about 1,000 feet of the existing Brine Line and constructing about 900 feet of 42-inch PVC lined Reinforced Concrete Pipe within the new re-aligned Schleisman Avenue.