Brine Line Relocation at Prado Dam

Value: $5,250,000.00 Contractor: Skanska Inc. Designer: CDM Inc. and Krieger & Stewart Inc. Completed: October 2008

Relocated the Brine Line at Prado Dam to eliminate conflicts with new facilities installed by the Corps of Engineers during the raising of the Dam. Pipelines were installed through the original dam outlet works which is no longer being used. New high density polyethylene pipe replaced 60 year old steel pipe in poor physical condition.